Third Party Order

Third Party Order


In third-party order processing, Business does not deliver the material requested by
the customer. Instead, business transfers the order to an external vendor, who sends
the materials directly to the customer and bills business accordingly.
a statistical goods receipt is necessary so that the requirement is consumed by this posting
There are no special features in the process of billing for third-party order processing.
The billing can be based on the order quantity or invoice quantity

High level overview

  1. Third Party Order
  2. Auto generation of PR
  3. Convert assigned PR to PO
  4.  Approval the Purchase Order
  5.  Statistical Goods Receipt
  6.   Vendor Invoice Verification
  7.  Incoming Customer Payment











Intercompany Stock Transfer

Intercompany Stock Transfer Business process Overview 

  • The stock transfer process begins with a requirement to transfer material from one plant to another Plant. Both plants belong to the same organization but different company codes. This request, in the form of a stock transfer requisition, may be created in the procuring plant automatically by MRP or manually by a buyer.
  • The material master must exist in both the procuring (receiving) plant and the providing (shipping) plant. Also, stock transfer purchase orders are not subject to approval like other purchase orders. A buyer validates the accuracy of the stock transfer purchase requisition and converts it into a stock transfer purchase order. 
  • A warehouse clerk at the shipping plant monitors the materials due to be shipped and creates deliveries as required.  Once a delivery is created, a pick list is generated, a warehouse clerk gathers the materials and confirms the picked quantities. Once the delivery is complete, the delivery quantities are issued, appropriate documentation is generated, and the goods are shipped.
  • Goods are received at the receiving plant referencing the delivery number on the shipping documents.
  • At the shipping plant the accounts receivable clerk creates an invoice and sends it to the procuring plant. At the procuring plant the accounts payable clerk receives this invoice with reference to the purchase order.
High Level Over view

  • Stock transport order processing in receiving plant
  • Delivery processing in supplying plant
  • Goods issue processing in the supplying plant
  • Checking Stock in Transit in the Receiving Plant Stock Overview
  • Billing processing in supplying plant
  • Goods receipt processing in receiving plan
  • Invoice verification processing in receiving plan






Tuesday 29 September 2015

Sub contracting Business Process

Subcontracting process involves sending raw components to a  subcontractor, or let purchase component and let vendor directly delivery component  to subcontractor for specific manufacturing processes, and receiving the value-added  finished material back into inventory
A subcontract purchase requisition is either generated via the Material Requirements  Planning (MRP) process or manually by a requestor. A buyer validates the accuracy of  the purchase requisition and converts it into a purchase order. The purchase order is  subject to approval based on predefined parameters prior to being issued to a vendor.
Component can be receipt into your own storage location or vendor can delivery to your  subcontractor inventory.
The consumption of sent components is recorded upon receipt of the value-added  finished material. The vendor sends the invoice for the services provided which is paid  during the normal payment cycle
High Level Key process flows as below
  1. Create Demand
  2. Create Sub Contracting PO
  3. Deliver Components to Subcontractor
  4. Receive Sub Contracted Goods
  5. Payment to Sub Contractor
Sub process Overviwe
1.       Purchase order creation based on a scheduled purchase requisition created by last 
2.        MRP run
3.       Purchase order approval (if required)
4.       Purchase order can delivery directly to subcontractor side
5.       Outbound delivery
6.       Goods issue for delivery and shipment (if required) to subcontractor
7.       On goods receipt, Goods receipt for purchase order delivered by subcontractor

8.       Invoice receipt by line item and Pay to vendor